|
|
|
|
| What needs to be done? | Deliverables |
| When must it happen>? | Constraints |
| How long will it take? | Estimates |
| Who is going to do it? | Resources |
| When will it happen? | Start and Finish Dates |
| How much will it cost | Rate * Assignment Effort |
When looking at the full scope of Project Management as defined by the PMBOK, MSP does not handle Communications, Procurement, and Risk Management.
3rd-Party Products making use of Project include:
|
Effective Executives Guide to Project 2000 : The Eight Steps for Using Microsoft Project 2000 to Organize, Manage and Finish Critically Important Projects [eBook] (Redmond: Microsoft Press, 2000)
by Nelson, Stephen L.; Coleman, Pat.; Dolliver, Kaarin
is still relevant even though the product version has changed.
|
|
| Exam : Microsoft Certification | MS class | IIL class |
|---|---|---|
| 70-632 : Microsoft Office Projects 2007, Managing Projects | 5927A | Orange Belt |
| 70-639 : Microsoft Office Project Server 2007, Configuration (for MS Certified Partners) focuses on technical installation of Project Server using SQL Server. | - | - |
| 70-633 : Enterprise Project Management with Microsoft Office Project Server 2007 | 5928A | Blue Belt |
| 70-634 : Pro: Microsoft Office Project Server 2007, Managing Projects and Programs | 5929A | Black Belt |
These are in place of the previous two levels of certification: (core and comprehensive) in 2000 and (basic and expert) in 2002.
Each of these 3 hour exams costs $125 USD. These are also available in French, German, Japanese, Castilian Spanish, and Chinese (Simplified).
|
Don't have MS Project installed?
|
|
|
Header Left : &[View] | &[Report] | &[Filter] |
|
| Fields | Task Views | Resource Views |
|---|---|---|
|
Duration (elapsed time)
Schedule (Start & Finish date) |
Calendar Detailed Gantt | Resource Graph |
| Work (time spent) Work Contours | Task Usage | Resource Usage Leveling Gantt |
| (Monetary) Costs |
Gantt
Tracking Gantt | Resource Sheet Resource Form |
| Outline_Code1...10 | WBS | - |
| Task Types
Predecessors and Successors (Dependencies) |
Network Diagram (PERT) Relationship Diagram | - |
|
|
| Shelly Cashman Spiral-bound books
Microsoft's Project 2007 Solution Center Download the Microsoft Office Project 2007 Service Pack 1 (SP1) |
|
|
|
| . |
|
|
|
|
| Field | Usage (Notes) |
|---|---|
| Flag8 | "Yes" if the task should appear on the Summary Gantt. |
| Indicators | (New to Project 2000) |
| Task Name | Expand and contract summary tasks by pressing Alt + Shift + [-] or [+]. |
| ResourceInitials | Used instead of Resource Names to limit width of text in charts and reports |
| Duration1, Duration2, Duration3 | Opt ... in PA_PERT Entry Table |
| Duration1, Start1, Finish1 | Opt ... in PA_Optimistic_Case Table |
| Duration2, Start2, Finish2 | Exp ... in PA_Expected_Case Table |
| Duration3, Start3, Finish3 | Pes ... in PA_Pessimistic_Case Table |
| Flag10 | "Text Above" in Rollup Table |
| Text1 | Comment |
| Start1 and Finish1 | A date which external organization, but not relevant
for scheduling. Note that both start and finish dates are needed for a milestone to appear. |
| Notes | To hold user text on miscellanous topics. Good to have just in case it's needed. |
|
Special Edition Using Microsoft Office Project 2003 (Macmillan, Feb 2004) by Tim Pyron
weighs in at 1248 pages
|
Views on the menu assigned by Microsoft/by default (after installation) are in shown in bold.
|
| Screen | View Name | Table | Filter | Note |
|---|---|---|---|---|
| -- | Task ... | Baseline | ||
| -- | Task ... | Constraint Dates | ||
| -- | -- | Cost | ||
| -- | -- | Earned Value | ||
| -- | Task ... | Export | ||
| -- | Resource ... | Export | ||
| -- | Task/Resc | Hyperlink | ||
| -- | Task ... | Schedule | ||
| -- | Task ... | Summary | ||
| -- | Resource ... | Summary | ||
| -- | Task ... | Tracking | ||
| -- | Task ... | Variance | ||
| -- | Resource ... | Variance | ||
| -- | -- | Work | ||
| -- | Resources... | Entry - Material Resources | ||
| -- | Resources... | Entry - Work Resources |
|
Planning a project,
Linked Fields Created After... Task Range... Working a project,
Incomplete Tasks When you're supervising workers,
Using Resource... Resource Group Managing project schedule,
Summary Tasks Milestones Critical Slipping Tasks Tasks with Deadlines Date Range... Should Start By... Should Start/Finish By... Shipped/Late Progress Unstarted Tasks Evaluating project cost,
Cost Overbudget Work Overbudget Closing a project,
Confirmed Unconfirmed Update Needed |
|
Instead of many links to the "Go-live" milestone, a vertical line is added so that it moves as the project is rescheduled. It is inserted using the Insert, Drawing function, Line option, and drawn on the screen. Then double-click on the vertical line to open the Format Drawing form, select the Size & Position tab, select the Task ID to attach the line, and the relative position to the bar. |
|
|
|
|
Full version of Adobe Acrobat to merge several reports output to a
pdf writer or use
SnagIt or other screen capture program to copy screens
to Excel or Word to create a combined report.
|
|
|
|
|
|
Microsoft Office Project 2003 Bible (John Wiley, 2004)
by Elaine J. Marmel
|
|
|
| Duration | Work | Units | Note |
|---|---|---|---|
| Duration1...10 | Work1...10 | Custom fields | |
| Actual Duration | Actual Work | ||
| -- | Baseline_Work Baseline1...10_Work | ||
| -- | Overtime Work | ||
| -- | Regular_Work | ||
| Remaining_Duration | Remaining_Work | ||
| -- | Remaining_Overtime_Work | ||
| - | Actual_Overtime_Work | ||
| Duration Variance | Work_Variance | ||
| Free Slack Total Slack | - | ||
| Leveling_Delay | - | - | |
| Assignment_Delay | - | Assignment_Units | |
| - | - | Max_Units | |
| - | Scheduled_Work | ||
| - | Percent_Work_Complete | ||
| - | Peak |
|
| Start Dates | Finish Dates | Usage |
|---|---|---|
| Start_Date | Finish_Date | |
| Start1...10 | Finish1...10 | Custom fields |
| Actual_Start | Actual_Finish | |
| Baseline_Start | Baseline_Finish | |
| Baseline1...10_Start | Baseline1...10_Finish | |
| Early_Start | Early_Finish | |
| Late_Start | Late_Finish | |
| Start_Variance | Finish_Variance | |
| Date1...10 | ... | |
| ... | Deadline | Appears as diamond indicator if Finish date is beyond this date. |
| Available_From | Available_To | - |
The Work_Contour field identifies the assignment timephased level contour used.
|
|
|
Edited contours can have a user-defined number of segments, each with a different duration. Segment durations are automatically changed when the duration is changed.
|
|
|
This explanation Assume the task is for two workers working together to build a stone wall with 5 rows of bricks in 150 minutes.
The first row (on the bottom) takes 20 minutes.
Both workers start at the same time.
But one of the workers leave after 60 minutes and the other completes the first three rows
75 minutes after they both started. Therefore, |
|
| The Reports > Visual Reports new in 2007 are Excel Pivot charts: To create a .mdb (MS-Access database), click "Save Data", then "Save Database". |
|
The Earned Value report generated by Microsoft Project:
The abbreviations:
A = Actual C = Cost W = Work P = Performed S = Scheduled V = Variance AC = At Completion Articles on the WWW about Earned Value:
|
Values for BAC is stored in the database field named "Baseline Cost" because the purpose of Earned Value is to, over time, guage variation from a baseline.
The outcomes defined by that "100%" is called the scope of the project.
Changes to the WBS (task hierarchy) can be changed without changing the baseline because they are separate concepts.
BCWS is calculated using what has been budgeted for the percent of completion achieved up to the report date, so it can also be called the "Planned Value Baseline".
MSP only calculates EVM baseline dollars ($). To derive the BCWP (EV), MSProject multiplies the Physical % Complete value by the baseline BCWS (PV). This is if in Tools > Options > Calculation > Earned Value... button > Default task Earned Value method is set to "Physical % Complete". This is reflected in the "Earned Value Method" column.
By default, P%C does not roll up to the summary task.
Each line on the EV graph is made by connecting values from reports issued at several different points over time.
|
|
To determine how well a project is going, the BCWS is compared against two other totals accumulated during the same range of time:
This approach enables managers to separate problems with rates of pay from problems with the number of hours worked on the project.
Comparing the EAC against the original BAC yields the VAC (Variance At Completion) which provides an early warning of "how bad it will get at the end if we keep this up."
|
| Task Name | Baseline Duration | Baseline Start | Baseline Finish | Baseline Work | Baseline Cost |
|---|
| Task Name | Duration | Constraint Type | Constraint Type |
|---|
| ID | Task Name | Fixed Cost | Fixed Cost Accural | Total Cost | Baseline Cost | Cost Variance | Actual Cost | Remaining Cost |
|---|
This is exported using the "Cost data by task" data map (internally titled the "Task Cost Table")
Note: Resource tables exclude fields "Fixed Cost", Cost ("Total Cost"), and "Fixed Cost Accural" (e.g., "Prorated" method, etc.).
| ID | Resource Name | Total Cost | Baseline Cost | Cost Variance | Actual Cost | Remaining Cost |
|---|
| Task Name | Leveling Delay | Duration | Start | Finish | Successors | Predecessors | Resource Names |
|---|
| Task/ Resource Name | BCWS | BCWP | ACWP | SV | CV | EAC | BAC | VAC |
|---|
|
| Resource Name | Type | Material Label | Initials | Group | Max Units | Standard Rate | Overtime Rate | Cost Per Use | Accrue At | Base Calendar | Code |
|---|
| Task Name | Duration | Start | Finish | Predecessors | Resource Names |
|---|
| Task ID | Task Name | Duration | Actual Finish | Constraint Type | Start | Finish | Predecessors | Resource Names |
|---|
| Resource Name | Type | Material Label | Initials | Group | Standard Rate | Cost Per Use | Accrue At | Code |
|---|
| Task/ Resource Name | Hyperlink | Hyperlink Address | Hyperlink SubAddress |
|---|
| Task Name | Duration | Text Above | Start | Predecessors | Resource Names |
|---|
| Task Name | Finish | Late Start | Late Finish | Free Slack | Total Slack |
|---|
| Task Name | Start | Finish | % Complete | Cost | Work |
|---|
| Task ID | Task Name | Duration | Start | Finish | % Comp. | Cost | Work |
|---|
| Resource Name | Group | Max Units | Peak | Standard Rate | Overtime Rate | Cost | Work |
|---|
| Task Name | Actual Finish | % Complete | Actual Duration | Remaining Duration | Actual Cost | Actual Work |
|---|
| Task Name | Work | Duration | Start | Finish |
|---|
| Resource Name | WorkDuration | Work |
|---|
| Task ID | Task Name | Start | Finish | Baseline Start | Baseline Finish | Start Var. | Finish Var. |
|---|
| Task Name | Work | Baseline Work | Work Variance | Actual Work | Remaining Work | % Work Complete |
|---|
Notice that the %" Work Complete" column on the Resource Table is in a different position than the Task Table.
| Resource Name | % Work Complete | Work | Overtime | Baseline Work | Work Variance | Actual Work | Remaining Work |
|---|
|
|
| Color Scheme | Centered | Columns | Stripes | Tabs | BGCOLOR | BODY TEXT | Title Font |
|---|---|---|---|---|---|---|---|
| Black | - | Y | Y | Y | #CCCCCC | #000000 | #000000 |
| Clay | - | Y | Y | Y | #E6CCCC | #800000 | #800000 |
| Cool Tone | - | Y | Y | Y | #3333CC | #FFFFFF | #99CC99 |
| Desert Light | - | - | - | Y | #FFCC99 | #CC6600 | #663399 |
| Glacier | Y | Y | Y | - | #9999CC | #660099 | #CCE6E6 |
| Ivy | Y | Y | Y | - | #CCCC99 | #336600 | #D6E0D6 |
| Maroon | Y | Y | Y | - | #CC9999 | #800000 | #E6CCCC |
| Mist Dark | Y | - | - | - | #336666 | #336666 | #ADA990 |
| Mist | Y | Y | Y | - | #ADA990 | #336666 | #D6E0E0 |
| Mulberry | - | Y | Y | - | #669999 | #660033 | #E0CCD6 |
| Navy | Y | Y | Y | - | #9999CC | #000080 | #CCCCE6 |
| Neon | Y | - | - | - | #000000 | #000080 | #99EEEE Dates
#EE00EE Report title |
| Vineyard | Y | - | - | Y | #669999 | #330066 | #CCCC00 |
Personally, I don't like these default designs:
Download "Wilsons Basic MSProject Report Template.html" into that folder,
then specify it as the "Base export on HTML template" on:
Each template file contain comment tags which are replaced during report creation. First comes the project attributes at the top of the page:
When you click the "Finish" button, MSProject adds values
to the right of the comment rather than replace the comment.
This means that you can't place the comment tags in the <TITLE> tag.
Then comes 3 sets of 2 sections:
I haven't figured out a way to change the font within tables, because MSProject replaces
each table comment tag with a complete table.
If you know, can you please email me? Thanks.
This Add-in for Microsoft Project 2000 lists differences between two versions of the same file, such as two possible Projections.
The default field configuration (and my preferred columns)
for 11 default maps which comes with the package are described in the next section:
|
|
| Core (Basic) | (Expert) | Comprehensive |
|---|---|---|
Creating a Project Plan
|
| Define the Project
|
Customizing a Project
|
| Define and Modify Tasks
|
General Project Management Concepts
|
|
|
Resource Management
| Specify and Assign Resources
|
|
Tracking a Project
|
| Track Progress
|
Communicating Project Information
|
| View and Report Project Status
|
Multi-Project Management
|
| Manage Multiple Projects
|
|
|
Add a New Project
Add a New Task
Review Existing Projects
Review Existing Tasks for a Resource
|
|
|
|
These sites by MVPs (Microsoft Valued Professionals) on Project, Gary Chefetz & Dale Howard self-published through their ms project experts.com two books on Enterprise Project Management:
Managing Enterprise Projects using Microsoft Office Project Server 2003
(Soho Corp, Oct 2004)
by Gary L. Chefetz, Dale A. Howard
$69
$47
|
|
|
|
|
|
Related Topics:
Keyboard Shortcuts
Project Software
Project Central
| Your first name: Your family name: Your location (city, country): Your Email address: |
Top of Page Thank you! | |||